Earliness penalties on a single machine subject to precedence constraints: SLK due date assignment
Gordon, V.S. and Strusevich, V.A. (1998) Earliness penalties on a single machine subject to precedence constraints: SLK due date assignment. Computers & Operations Research, 26 (2). pp. 157-177. ISSN 0305-0548 (doi:10.1016/S0305-0548(98)00055-0)
Full text not available from this repository.Abstract
The paper considers the single machine due date assignment and scheduling problems with n jobs in which the due dates are to be obtained from the processing times by adding a positive slack q. A schedule is feasible if there are no tardy jobs and the job sequence respects given precedence constraints. The value of q is chosen so as to minimize a function ϕ(F,q) which is non-decreasing in each of its arguments, where F is a certain non-decreasing earliness penalty function. Once q is chosen or fixed, the corresponding scheduling problem is to find a feasible schedule with the minimum value of function F. In the case of arbitrary precedence constraints the problems under consideration are shown to be NP-hard in the strong sense even for F being total earliness. If the precedence constraints are defined by a series-parallel graph, both scheduling and due date assignment problems are proved solvable in time, provided that F is either the sum of linear functions or the sum of exponential functions. The running time of the algorithms can be reduced to if the jobs are independent.
Scope and purpose
We consider the single machine due date assignment and scheduling problems and design fast algorithms for their solution under a wide range of assumptions. The problems under consideration arise in production planning when the management is faced with a problem of setting the realistic due dates for a number of orders. The due dates of the orders are determined by increasing the time needed for their fulfillment by a common positive slack. If the slack is set to be large enough, the due dates can be easily maintained, thereby producing a good image of the firm. This, however, may result in the substantial holding cost of the finished products before they are brought to the customer. The objective is to explore the trade-off between the size of the slack and the arising holding costs for the early orders.
Item Type: | Article |
---|---|
Uncontrolled Keywords: | single machine scheduling, due date assignment, precedence constraints, earliness penalties |
Subjects: | Q Science > QA Mathematics |
Pre-2014 Departments: | School of Computing & Mathematical Sciences School of Computing & Mathematical Sciences > Department of Mathematical Sciences School of Computing & Mathematical Sciences > Statistics & Operational Research Group |
Related URLs: | |
Last Modified: | 14 Oct 2016 08:59 |
URI: | http://gala.gre.ac.uk/id/eprint/128 |